Estate Delivery and Construction Progress
Stage 1 and 2 are being delivered simultaneously, alongside external sewerage infrastructure along Windsor Street, and the development of the new Cemetery Road connecting the estate directly to town via the golf course.
To see how the estate is progressing, check out the construction update and site photos below!
August 2026 Construction Progress Update
Stage 1 and 2 has progressed consistently, having completed earthworks, water mains, and major pipework, currently proceeding with roadworks, and service crossings.
We were able to progress more on Cemetery Road earthworks with recent dry weather, significantly lifting the road level.
For external work along Windsor Street, hard rock drilling and pipe welding has been completed, now continuing the installation of rising and water mains.